Files
openclaw-workspace-2026/outputs/beawit_intune_client_summary_kmcc.md
T
JC Beasley 9891d7e4d5 Weekly sync: July 12-19 changes
- Updated DREAMS.md and MEMORY.md with new entries
- Added daily dreaming session corpus (2026-07-05 through 2026-07-18)
- Added deep/light/REM dream analysis files for July 6-19
- Added Intune rollout outputs for KMCC client
- Added Vault API integration scripts and documentation
- Added container update playbook (update-containers.yml)
- Added .gitignore for generated/noise files
2026-07-19 08:49:43 -07:00

5.2 KiB
Raw Blame History

Kelly McNutt Consulting — Intune Device Enrollment Status Report

Prepared by: Beawit Consulting
Date: July 16, 2026
Reporting Period: Rollout Phase — July 21, 2026 to October 3, 2026


Executive Summary

Kelly McNutt Consulting is implementing Microsoft Intune device management across all 63 users. The rollout follows a structured weekly approach beginning July 21, 2026, with completion targeted for October 3, 2026.

Current Status:

  • 6 users fully enrolled and operational
  • 7 users in pilot phase (emails sent, enrollment in progress)
  • 50 users scheduled across 10 weekly waves
  • 1 user requires verification before enrollment

Enrollment Status Overview

Status Count Percentage
Enrolled — Complete 6 9.5%
📧 Pilot Phase — Email Sent 7 11.1%
Scheduled for Enrollment 50 79.4%
⚠️ Verification Required 1 1.6%
Total Users 63 100%

Completed Enrollments

The following users are fully enrolled in Intune and operational:

Name Device Ownership
Alex Mckinstry A_MCKINSTRY-KMC Corporate
Emily Jiang DESKTOP-AVDG2PS Corporate
Jasper Bolster JASPER-LAPTOP Corporate
Jennifer Nickel SAMSUNG-NICKEL Personal
Rebecca Skjothaug BECCA_SKJOTHAUG Corporate
Victor Szabo DESKTOP-OR73OFU Corporate

Weekly Rollout Schedule

Phase 1 — Pilot (July 2125)

7 users have received enrollment instructions. Focus this week is follow-up, troubleshooting, and driving completion.

Name Email Status
Alex Mcnutt a.mcnutt@kmccostandrisk.com Pending Enrollment
Andy Fairbairn andy@kmccostandrisk.com Pending Enrollment
Ariana Ince ariana@kmccostandrisk.com Pending Enrollment
Brandon Zink brandon@kmccostandrisk.com Pending Enrollment
Bruce Patterson bruce@kmccostandrisk.com Pending Enrollment
Christine Hutton c.hutton@kmccostandrisk.com Pending Enrollment
Christopher Parr christopher@kmccostandrisk.com Pending Enrollment

Phase 2 — Weekly Rollout (July 28 October 3)

Remaining 50 users are scheduled in 10 weekly waves of 5 users each:

Week Dates Users Key Notes
Week 2 Jul 28Aug 1 5 David Rodriguez, David Ryan, Dennis Curtin, Don Hamann, Drew Clark
Week 3 Aug 48 5 Ed Ritchie — verification required before enrollment
Week 4 Aug 1115 5 Jacob Hinch, Jacqueline Fairbairn, Jared Englehart, Jeremy Zink, Reg Carson
Week 5 Aug 1822 5 Jerred DeJong, Jerry Englehart, Jesse Olstead, Jesse Sherwood, Josh Gable
Week 6 Aug 2529 5 Josh Keogh, Josh Parsons, Kelly Mcnutt, Kent Kruse, Kent Werle
Week 7 Sep 15 5 Kyle Kankanton, Kyle Stone, Leann Vigna, Lee Zink, Mario Escalera
Week 8 Sep 812 5 Mark Curtiss, Martijn Bolster, Mathers Heuck, Maximus Sherwood, Megan Donegan
Week 9 Sep 1519 5 Mike Schoeff, Miles Mauldin, Paola Ryan, Peter Elza, Peter Sanderson
Week 10 Sep 2226 5 Rachelle Trujillo, Raffy Hammett, Ralph Salamie, Robb Swenson, Robert Barnard
Week 11 Sep 29Oct 3 5 Ron Adair, Ross Gilmour, Russ Winger, Troy Marble, Victoria McNutt

Weekly Cadence

Each week follows a consistent rhythm:

Day Activity
Monday Kickoff — enrollment instructions sent to scheduled users
TuesdayFriday Enrollment window — users complete Intune enrollment
Friday Post-enrollment satisfaction survey
Weekend Review results, resolve blockers, plan next wave

Items Requiring Attention

⚠️ Verification Required — Ed Ritchie

  • User: Ed Ritchie (e.ritchie@kmccostandrisk.com)
  • Scheduled: Week 3 (August 48)
  • Issue: Verification required before enrollment can proceed
  • Action: Resolve verification status before enrollment week begins

📋 Week 1 Follow-Up

  • Users: 7 pilot participants
  • Status: Emails sent, awaiting enrollment completion
  • Action: Follow up on Monday, July 21 to confirm enrollment status and resolve any issues

Project Timeline

Milestone Date
Pilot Phase Start July 21, 2026
Weekly Rollout Begins July 28, 2026
Final Wave (Week 11) September 29 October 3, 2026
Project Completion October 3, 2026

Total Duration: 11 weeks


Next Steps

  1. July 21: Follow up with 7 pilot users on enrollment status
  2. July 28: Begin Week 2 rollout (5 new users)
  3. Before August 4: Resolve Ed Ritchie verification requirement
  4. Ongoing: Weekly kickoffs, enrollment tracking, and survey collection
  5. October 3: Final rollout completion and project closeout

Contact & Support

For questions or issues during enrollment, users should contact:

Beawit Consulting — IT Support
Kelly McNutt Consulting Internal IT — Primary contact for scheduling and troubleshooting


Report generated from live Intune Device Management tracking system
Grist tracker: https://grist.beawit.net/o/docs-6/wmBGUbgBveCd/