# Kelly McNutt Consulting β€” Intune Device Enrollment Status Report **Prepared by:** Beawit Consulting **Date:** July 16, 2026 **Reporting Period:** Rollout Phase β€” July 21, 2026 to October 3, 2026 --- ## Executive Summary Kelly McNutt Consulting is implementing Microsoft Intune device management across all 63 users. The rollout follows a structured weekly approach beginning July 21, 2026, with completion targeted for October 3, 2026. **Current Status:** - **6 users** fully enrolled and operational - **7 users** in pilot phase (emails sent, enrollment in progress) - **50 users** scheduled across 10 weekly waves - **1 user** requires verification before enrollment --- ## Enrollment Status Overview | Status | Count | Percentage | |--------|-------|------------| | βœ… Enrolled β€” Complete | 6 | 9.5% | | πŸ“§ Pilot Phase β€” Email Sent | 7 | 11.1% | | ⏳ Scheduled for Enrollment | 50 | 79.4% | | ⚠️ Verification Required | 1 | 1.6% | | **Total Users** | **63** | **100%** | --- ## Completed Enrollments The following users are fully enrolled in Intune and operational: | Name | Device | Ownership | |------|--------|-----------| | Alex Mckinstry | A_MCKINSTRY-KMC | Corporate | | Emily Jiang | DESKTOP-AVDG2PS | Corporate | | Jasper Bolster | JASPER-LAPTOP | Corporate | | Jennifer Nickel | SAMSUNG-NICKEL | Personal | | Rebecca Skjothaug | BECCA_SKJOTHAUG | Corporate | | Victor Szabo | DESKTOP-OR73OFU | Corporate | --- ## Weekly Rollout Schedule ### Phase 1 β€” Pilot (July 21–25) **7 users** have received enrollment instructions. Focus this week is follow-up, troubleshooting, and driving completion. | Name | Email | Status | |------|-------|--------| | Alex Mcnutt | a.mcnutt@kmccostandrisk.com | Pending Enrollment | | Andy Fairbairn | andy@kmccostandrisk.com | Pending Enrollment | | Ariana Ince | ariana@kmccostandrisk.com | Pending Enrollment | | Brandon Zink | brandon@kmccostandrisk.com | Pending Enrollment | | Bruce Patterson | bruce@kmccostandrisk.com | Pending Enrollment | | Christine Hutton | c.hutton@kmccostandrisk.com | Pending Enrollment | | Christopher Parr | christopher@kmccostandrisk.com | Pending Enrollment | ### Phase 2 β€” Weekly Rollout (July 28 – October 3) Remaining **50 users** are scheduled in **10 weekly waves of 5 users each**: | Week | Dates | Users | Key Notes | |------|-------|-------|-----------| | Week 2 | Jul 28–Aug 1 | 5 | David Rodriguez, David Ryan, Dennis Curtin, Don Hamann, Drew Clark | | Week 3 | Aug 4–8 | 5 | **Ed Ritchie** β€” verification required before enrollment | | Week 4 | Aug 11–15 | 5 | Jacob Hinch, Jacqueline Fairbairn, Jared Englehart, Jeremy Zink, Reg Carson | | Week 5 | Aug 18–22 | 5 | Jerred DeJong, Jerry Englehart, Jesse Olstead, Jesse Sherwood, Josh Gable | | Week 6 | Aug 25–29 | 5 | Josh Keogh, Josh Parsons, Kelly Mcnutt, Kent Kruse, Kent Werle | | Week 7 | Sep 1–5 | 5 | Kyle Kankanton, Kyle Stone, Leann Vigna, Lee Zink, Mario Escalera | | Week 8 | Sep 8–12 | 5 | Mark Curtiss, Martijn Bolster, Mathers Heuck, Maximus Sherwood, Megan Donegan | | Week 9 | Sep 15–19 | 5 | Mike Schoeff, Miles Mauldin, Paola Ryan, Peter Elza, Peter Sanderson | | Week 10 | Sep 22–26 | 5 | Rachelle Trujillo, Raffy Hammett, Ralph Salamie, Robb Swenson, Robert Barnard | | Week 11 | Sep 29–Oct 3 | 5 | Ron Adair, Ross Gilmour, Russ Winger, Troy Marble, Victoria McNutt | --- ## Weekly Cadence Each week follows a consistent rhythm: | Day | Activity | |-----|----------| | **Monday** | Kickoff β€” enrollment instructions sent to scheduled users | | **Tuesday–Friday** | Enrollment window β€” users complete Intune enrollment | | **Friday** | Post-enrollment satisfaction survey | | **Weekend** | Review results, resolve blockers, plan next wave | --- ## Items Requiring Attention ### ⚠️ Verification Required β€” Ed Ritchie - **User:** Ed Ritchie (e.ritchie@kmccostandrisk.com) - **Scheduled:** Week 3 (August 4–8) - **Issue:** Verification required before enrollment can proceed - **Action:** Resolve verification status before enrollment week begins ### πŸ“‹ Week 1 Follow-Up - **Users:** 7 pilot participants - **Status:** Emails sent, awaiting enrollment completion - **Action:** Follow up on Monday, July 21 to confirm enrollment status and resolve any issues --- ## Project Timeline | Milestone | Date | |-----------|------| | **Pilot Phase Start** | July 21, 2026 | | **Weekly Rollout Begins** | July 28, 2026 | | **Final Wave (Week 11)** | September 29 – October 3, 2026 | | **Project Completion** | October 3, 2026 | **Total Duration:** 11 weeks --- ## Next Steps 1. **July 21:** Follow up with 7 pilot users on enrollment status 2. **July 28:** Begin Week 2 rollout (5 new users) 3. **Before August 4:** Resolve Ed Ritchie verification requirement 4. **Ongoing:** Weekly kickoffs, enrollment tracking, and survey collection 5. **October 3:** Final rollout completion and project closeout --- ## Contact & Support For questions or issues during enrollment, users should contact: **Beawit Consulting** β€” IT Support **Kelly McNutt Consulting Internal IT** β€” Primary contact for scheduling and troubleshooting --- *Report generated from live Intune Device Management tracking system* *Grist tracker: https://grist.beawit.net/o/docs-6/wmBGUbgBveCd/*